by Blair Gisi, Esq.
SouthLaw, P.C.
USFN Member (IA, KS, MO, NE)
The Kansas Court of Appeals in In re A
Purported Lien Against Prop. of Dist. at City Ctr., LLC, 2020 Kan. App.
LEXIS 13 (Ct. App. Feb. 28, 2020) reversed the district court in an interesting
case regarding an allegedly fraudulent mechanic’s lien.
This case began with a recognizable fact pattern where a construction company
was contracted to build a mixed-use development. The contractor then hired a subcontractor to
supply steel and labor. As is often the
case, change orders began to be submitted and approved resulting in a total
that exceeded the original contract terms.
Subsequently, the subcontractor filed a mechanic’s lien for unpaid labor and
cost materials totaling over $400,000 – which was the difference between the
value of the work the subcontractor believed it had completed and the amount
already paid. However, as part of the
supporting documentation filed with the mechanic’s lien, the subcontractor
failed to include itemizations evidencing the full value of the purported
additional labor, leaving a gap of approximately $25,000.
Where this case takes an interesting turn is that instead of the contractor
challenging the mechanic’s in the traditional way under K.S.A. §60-1108 or the
subcontractor amending or foreclosing the mechanic’s lien pursuant to K.S.A.
§§60-1105(a) or 60-1106, the contractor filed a motion claiming the lien was
fraudulent under K.S.A. 2019 Supp. §58-4301.
K.S.A. §58-4301 was enacted to address issues with militias and “common-law
type groups” who file and record fraudulent liens against properties in an
effort to harass property owners and delay judicial proceedings. The key issue to analyze under this statute
with regards to whether a document is “fraudulent” is whether the document or
instrument is provided for by the constitution or laws of Kansas or the United
States. Legitimacy of the actual
document is not weighed or analyzed.
The benefit to the contractor here (and presumably why this route was chosen)
is that the statute provides for an expedited review and does not require a
filing fee. If there is substantial
compliance with the statute, then, “the court’s findings may be made solely on
a review of the documentation or instrument attached to the motion and without
hearing any testimonial evidence.”
K.S.A. §58-4301(b). The Motion
can also be heard ex parte without delay
or notice of any kind.
Relying on its authority to expeditiously review the matter, the district court
granted the contractor’s motion removing the lien before the subcontractor
could even object or otherwise respond; basing its decision on the
subcontractor’s failure to account for the $25,000 in additional work and
finding the mechanic’s lien insufficient to provide notice for what claims were
actually owed.
The problem for the contractor (and the district court), however, was that the
mechanic’s lien at issue was and is a document provided for by Kansas law,
therefore, the decision to remove the lien as “fraudulent” was an error and the
case was remanded. The district court
should not have even looked at whether the lien itself was sufficient or
statutorily compliant.
In applying this case to the servicing industry, the important take away here
is that even where a mechanic’s lien appears to be faulty or even fraudulent,
the shortcut for the lien removal provided under K.S.A. §58-4301 has to be
avoided. The Court will not look at the
validity of a mechanic’s lien under that statute since we now know that the
mechanic’s lien is provided for under Kansas law.
Copyright © 2020 USFN. All rights reserved.
Spring 2020 USFN Report